When the contract plans and standard specifications contain inconsistencies, which document should be prioritized?

Prepare for the FDOT Plan Reading Exam with focused study tools. Utilize flashcards and multiple-choice questions, complete with helpful hints and detailed explanations. Gear up to excel in your exam!

When faced with inconsistencies between the contract plans and standard specifications, prioritizing the contract plans is essential. The contract plans provide the visual representation and specific details about the project, including dimensions, locations, and other critical information necessary for the construction process. They serve as a binding agreement between the contractor and the owner, detailing the specific expectations and requirements of the project.

In construction projects, the contract plans are typically viewed as the primary document. They are usually more project-specific and may contain details that the standard specifications, which are more general in nature, do not address. By referring to the contract plans first, project stakeholders can ensure that the execution aligns with the intended design and project goals.

Standard specifications, while important for general guidelines and construction techniques, often do not cover the specific scenario presented in a contract plan. Since contract plans are tailored to the specific project, they take precedence in resolving any discrepancies found within the documentation.

Subscribe

Get the latest from Examzify

You can unsubscribe at any time. Read our privacy policy